Action Date | Action Description |
---|---|
Jun 13, 2022 | Assent Application Received |
Jun 15, 2022 | Administrative Review for Completeness |
Jun 17, 2022 | Bio Team Review for Completeness |
Jun 17, 2022 | Application Accepted |
Jun 21, 2022 | Project Manager |
Jul 21, 2022 | HPHC Historical Preservation Comments/Concerns |
Aug 02, 2022 | HPHC Historical Preservation No Effect |
Aug 17, 2022 | Additional Information Requested from Applicant |
Sep 15, 2022 | Correspondence Received |
Feb 23, 2023 | Additional Information Received |
Jun 30, 2023 | Biologist Report |
Jul 03, 2023 | Typist for Processing |
Jul 05, 2023 | Executive Sign Off |
Jul 05, 2023 | Sent to Photo Copy |
Jul 05, 2023 | Permit Approved |
Jul 07, 2023 | Permit Mailed |
Jul 31, 2023 | Land Evidence Date |
Jun 14, 2024 | Commencement of Work Notice received |