Action Date | Action Description |
---|---|
Jun 30, 2022 | Freshwater Wetland - Preliminary Determination |
Jul 06, 2022 | Administrative Review for Completeness |
Jul 11, 2022 | Bio Team Review for Completeness |
Jul 11, 2022 | Deficient Application - Owner Notification Sent |
Nov 22, 2022 | Deficiency Response Received |
Dec 12, 2022 | Bio Team Review for Completeness |
Dec 12, 2022 | Application Accepted |
Dec 12, 2022 | Project Manager |
Jan 11, 2023 | HPHC Historical Preservation No Effect |
Mar 06, 2023 | Biologist Report |
Mar 23, 2023 | Typist for Processing |
Mar 23, 2023 | Executive Sign Off |
Mar 23, 2023 | Sent to Photo Copy |
Mar 23, 2023 | Permit Approved |
Mar 28, 2023 | Permit Mailed |
Apr 10, 2023 | Land Evidence Date |
Jun 26, 2023 | Commencement of Work Notice received |