Action Date | Action Description |
---|---|
Jul 13, 2022 | CHA Worksheet received |
Jul 13, 2022 | Assent Application Received |
Jul 19, 2022 | Administrative Review for Completeness |
Jul 21, 2022 | Bio Team Review for Completeness |
Jul 21, 2022 | Application Accepted |
Jul 21, 2022 | Project Manager |
Aug 17, 2022 | HPHC Historical Preservation No Effect |
Aug 26, 2022 | Additional Information Requested from Applicant |
Aug 30, 2022 | Additional Information Received |
Oct 12, 2022 | Biologist Report |
Oct 17, 2022 | Typist for Processing |
Oct 17, 2022 | Executive Sign Off |
Oct 17, 2022 | Sent to Photo Copy |
Oct 17, 2022 | Permit Approved |
Oct 19, 2022 | Permit Mailed |
Oct 20, 2022 | Land Evidence Date |