Action Date | Action Description |
---|---|
Aug 04, 2022 | Assent Application Received |
Aug 11, 2022 | Administrative Review for Completeness |
Aug 11, 2022 | CHA Worksheet received |
Aug 16, 2022 | Eng Team Review for Completeness |
Aug 16, 2022 | Application Accepted |
Aug 18, 2022 | Category B assigned |
Aug 19, 2022 | Project Manager |
Aug 31, 2022 | HPHC Historical Preservation No Effect |
Oct 22, 2022 | Public Notice End Date |
Nov 02, 2022 | Water Quality Certification |
Feb 24, 2023 | Additional Information Received |
Mar 16, 2023 | Mail Agenda Notice |
Mar 28, 2023 | Continued application |
Mar 28, 2023 | Semi-Monthly Meeting Date Scheduled |
Apr 04, 2023 | Mail Agenda Notice |
Apr 24, 2023 | Semi-Monthly Meeting Date Scheduled |
May 18, 2023 | Engineering Report |
May 23, 2023 | Typist for Processing |
May 23, 2023 | Executive Sign Off |
May 23, 2023 | Sent to Photo Copy |
May 23, 2023 | Permit Approved |
Jun 23, 2023 | Permit Mailed |
Jun 26, 2023 | Land Evidence Date |
Aug 24, 2023 | Commencement of Work Notice received |