Dock Post-Construction Certification by Engineer received. | |
Aug 29, 2022 | Assent Application Received |
Aug 29, 2022 | CHA Worksheet received |
Sep 02, 2022 | Administrative Review for Completeness |
Sep 08, 2022 | Bio Team Review for Completeness |
Sep 08, 2022 | Application Accepted |
Sep 13, 2022 | Project Manager |
Oct 18, 2022 | HPHC Historical Preservation No Effect |
Oct 24, 2022 | Biologist Report |
Oct 26, 2022 | Typist for Processing |
Oct 26, 2022 | Executive Sign Off |
Oct 26, 2022 | Sent to Photo Copy |
Oct 26, 2022 | Permit Approved |
Oct 26, 2022 | Permit Mailed |
Nov 03, 2022 | Land Evidence Date |