Action Date | Action Description |
---|---|
Sep 16, 2022 | Assent Application Received |
Sep 21, 2022 | Administrative Review for Completeness |
Sep 22, 2022 | Bio Team Review for Completeness |
Sep 26, 2022 | Project Manager |
Sep 26, 2022 | Application Accepted |
Sep 26, 2022 | Project Manager |
Oct 18, 2022 | HPHC Historical Preservation No Effect |
Nov 01, 2022 | Additional Information Requested from Applicant |
Jan 17, 2023 | Additional Information Received |
Jan 27, 2023 | Plans Received |
Mar 15, 2023 | Biologist Report |
Mar 27, 2023 | Typist for Processing |
Mar 27, 2023 | Executive Sign Off |
Mar 27, 2023 | Sent to Photo Copy |
Mar 27, 2023 | Permit Approved |
Mar 30, 2023 | Permit Mailed |
Oct 31, 2023 | Land Evidence Date |