Action Date | Action Description |
---|---|
Sep 22, 2022 | Assent Application Received |
Oct 24, 2022 | Administrative Review for Completeness |
Oct 24, 2022 | Deficient Application - Owner Notification Sent |
Nov 04, 2022 | Deficiency Response Received |
Nov 18, 2022 | Bio Team Review for Completeness |
Nov 21, 2022 | Deficient Application - Owner Notification Sent |
Jul 05, 2023 | Phone Call |
Jul 05, 2023 | Correspondence Mailed/Faxed/E-mailed |
Oct 18, 2023 | Deficiency Response Received |
Oct 18, 2023 | Bio Team Review for Completeness |
Oct 18, 2023 | Application Accepted |
Oct 18, 2023 | Project Manager |
Oct 18, 2023 | HPHC Historical Preservation No Effect |
Nov 09, 2023 | Correspondence Mailed/Faxed/E-mailed |
Dec 20, 2023 | Additional Information Requested from Applicant |
Feb 02, 2024 | Note to File |
Mar 07, 2024 | Biologist Report |
Mar 08, 2024 | Typist for Processing |
Mar 08, 2024 | Executive Sign Off |
Mar 08, 2024 | Sent to Photo Copy |
Mar 08, 2024 | Permit Approved |
Mar 12, 2024 | Permit Mailed |
Apr 08, 2024 | Land Evidence Date |