Action Date | Action Description |
---|---|
Oct 03, 2022 | Assent Application Received |
Oct 18, 2022 | Additional Information Received |
Nov 03, 2022 | Phone Call |
Nov 04, 2022 | Administrative Review for Completeness |
Nov 18, 2022 | Bio Team Review for Completeness |
Nov 18, 2022 | Application Accepted |
Nov 18, 2022 | Project Manager |
Dec 09, 2022 | Biologist Report |
Dec 13, 2022 | HPHC Historical Preservation No Effect |
Dec 28, 2022 | Executive Sign Off |
Dec 28, 2022 | Sent to Photo Copy |
Dec 28, 2022 | Permit Approved |
Dec 28, 2022 | Typist for Processing |
Dec 30, 2022 | Permit Mailed |
Feb 03, 2023 | Commencement of Work Notice received |
Feb 28, 2023 | Land Evidence Date |