Action Date | Action Description |
---|---|
Nov 09, 2022 | CHA Worksheet received |
Nov 09, 2022 | Assent Application Received |
Nov 15, 2022 | Administrative Review for Completeness |
Nov 22, 2022 | Bio Team Review for Completeness |
Nov 22, 2022 | Project Manager |
Nov 22, 2022 | Application Accepted |
Jan 03, 2023 | HPHC Historical Preservation No Effect |
Jan 10, 2023 | Biologist Report |
Jan 11, 2023 | Typist for Processing |
Jan 11, 2023 | Executive Sign Off |
Jan 11, 2023 | Sent to Photo Copy |
Jan 11, 2023 | Permit Approved |
Jan 12, 2023 | Permit Mailed |
Oct 02, 2023 | Land Evidence Date |
Dec 22, 2023 | Modification Request |
Jan 09, 2024 | Additional Information Received |
Jan 10, 2024 | Administrative Review for Completeness |
Jan 22, 2024 | Bio Team Review for Completeness |
Jan 22, 2024 | Project Manager |
Jan 22, 2024 | Application Accepted |
Jan 30, 2024 | HPHC Historical Preservation No Effect |
Mar 05, 2024 | Biologist Report |
Mar 08, 2024 | Typist for Processing |
Mar 08, 2024 | Executive Sign Off |
Mar 08, 2024 | Sent to Photo Copy |
Mar 08, 2024 | Permit Approved |
Mar 12, 2024 | Permit Mailed |
Mar 22, 2024 | Land Evidence Date |