Action Date | Action Description |
---|---|
Dec 07, 2022 | Assent Application Received |
Dec 09, 2022 | Administrative Review for Completeness |
Jan 11, 2023 | Bio Team Review for Completeness |
Jan 11, 2023 | Application Accepted |
Jan 11, 2023 | Project Manager |
Jan 17, 2023 | HPHC Historical Preservation No Effect |
Feb 22, 2023 | Additional Information Requested from Applicant |
Feb 28, 2023 | Correspondence Received |
Mar 01, 2023 | Correspondence Mailed/Faxed/E-mailed |
May 19, 2023 | Additional Information Received |
Jun 01, 2023 | Biologist Report |
Jun 06, 2023 | Typist for Processing |
Jun 06, 2023 | Executive Sign Off |
Jun 06, 2023 | Sent to Photo Copy |
Jun 06, 2023 | Permit Approved |
Jun 08, 2023 | Permit Mailed |
Jun 26, 2023 | Land Evidence Date |
Jul 17, 2023 | Commencement of Work Notice received |