Action Date | Action Description |
---|---|
Land Evidence Date | |
Dec 09, 2022 | Buffer Zone Management Application Received |
Dec 14, 2022 | Administrative Review for Completeness |
Dec 15, 2022 | Bio Team Review for Completeness |
Dec 15, 2022 | Deficient Application - Owner Notification Sent |
Dec 21, 2022 | Deficient Application Picked Up |
Apr 20, 2023 | Deficiency Response Received |
Apr 28, 2023 | Correspondence Mailed/Faxed/E-mailed |
May 01, 2023 | Additional Information Received |
Jul 11, 2023 | Bio Team Review for Completeness |
Jul 12, 2023 | Deficient Application - Owner Notification Sent |
Aug 17, 2023 | Deficient Application Picked Up |
Sep 22, 2023 | Deficiency Response Received |
Oct 11, 2023 | Bio Team Review for Completeness |
Oct 11, 2023 | Application Accepted |
Oct 11, 2023 | Project Manager |
Oct 19, 2023 | HPHC Historical Preservation No Effect |
Oct 23, 2023 | Additional Information Requested from Applicant |
Oct 27, 2023 | Additional Information Received |
Dec 20, 2023 | Biologist Report |
Dec 26, 2023 | Typist for Processing |
Dec 26, 2023 | Executive Sign Off |
Dec 26, 2023 | Sent to Photo Copy |
Dec 26, 2023 | Permit Approved |
Dec 28, 2023 | Permit Mailed |
Mar 19, 2024 | Commencement of Work Notice received |