Action Date | Action Description |
---|---|
Jan 25, 2023 | Maintenance Certification Request |
Jan 27, 2023 | Administrative Review for Completeness |
Feb 03, 2023 | Eng Team Review for Completeness |
Feb 03, 2023 | Deficient Application - Owner Notification Sent |
May 08, 2023 | Deficiency Response Received |
May 16, 2023 | Eng Team Review for Completeness |
May 16, 2023 | Application Accepted |
May 16, 2023 | Project Manager |
May 16, 2023 | Category B assigned |
May 31, 2023 | 30 day Public Notice Issued |
Jun 14, 2023 | HPHC Historical Preservation No Effect |
Jun 30, 2023 | Public Notice End Date |
Aug 01, 2023 | Dock/1.1.6 Review approval |
Jan 05, 2024 | Typist for Processing |
Jan 05, 2024 | Executive Sign Off |
Jan 05, 2024 | Sent to Photo Copy |
Jan 05, 2024 | Permit Approved |
Jan 05, 2024 | Engineering Report |
Jan 09, 2024 | Permit Mailed |
Jan 31, 2024 | Land Evidence Date |