Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Feb 01, 2023 | Assent Application Received |
Feb 03, 2023 | Administrative Review for Completeness |
Feb 09, 2023 | Bio Team Review for Completeness |
Feb 09, 2023 | Application Accepted |
Feb 17, 2023 | Project Manager |
Feb 28, 2023 | HPHC Historical Preservation No Effect |
Mar 14, 2023 | 30 day Public Notice Issued |
Apr 14, 2023 | Public Notice End Date |
Aug 01, 2023 | Dock/1.1.6 Review approval |
Aug 15, 2023 | Additional Information Requested from Applicant |
Aug 31, 2023 | Correspondence Received |
Sep 07, 2023 | Additional Information Received |
Sep 13, 2023 | Biologist Report |
Sep 19, 2023 | Typist for Processing |
Sep 19, 2023 | Executive Sign Off |
Sep 19, 2023 | Sent to Photo Copy |
Sep 19, 2023 | Permit Approved |
Sep 25, 2023 | Permit Mailed |
Oct 23, 2023 | Land Evidence Date |