Action Date | Action Description |
---|---|
Feb 28, 2023 | Maintenance Certification Request |
Mar 02, 2023 | Administrative Review for Completeness |
Mar 08, 2023 | Bio Team Review for Completeness |
Mar 08, 2023 | Project Manager |
Mar 08, 2023 | Application Accepted |
Apr 25, 2023 | Biologist Report |
May 16, 2023 | Typist for Processing |
May 16, 2023 | HPHC Historical Preservation No Effect |
May 16, 2023 | Executive Sign Off |
May 16, 2023 | Sent to Photo Copy |
May 16, 2023 | Permit Approved |
May 18, 2023 | Permit Mailed |
Oct 04, 2023 | Land Evidence Date |