Action Date | Action Description |
---|---|
Mar 14, 2023 | Maintenance Certification Request |
Mar 16, 2023 | Administrative Review for Completeness |
Apr 12, 2023 | Bio Team Review for Completeness |
Apr 12, 2023 | Application Accepted |
Apr 12, 2023 | Project Manager |
Apr 19, 2023 | HPHC Historical Preservation No Effect |
Aug 23, 2023 | Biologist Report |
Aug 28, 2023 | Typist for Processing |
Aug 28, 2023 | Executive Sign Off |
Aug 28, 2023 | Sent to Photo Copy |
Aug 28, 2023 | Permit Approved |
Aug 28, 2023 | Permit Mailed |