Action Date | Action Description |
---|---|
Apr 06, 2023 | Buffer Zone Management Application Received |
Apr 06, 2023 | Administrative Review for Completeness |
Apr 13, 2023 | Bio Team Review for Completeness |
Apr 13, 2023 | Application Accepted |
Apr 13, 2023 | Project Manager |
Apr 17, 2023 | HPHC Historical Preservation No Effect |
Apr 20, 2023 | Correspondence Mailed/Faxed/E-mailed |
Apr 21, 2023 | Biologist Report |
Apr 24, 2023 | Typist for Processing |
Apr 24, 2023 | Executive Sign Off |
Apr 24, 2023 | Sent to Photo Copy |
Apr 24, 2023 | Permit Approved |
Apr 24, 2023 | Permit Mailed |
May 15, 2023 | Land Evidence Date |
May 16, 2023 | Commencement of Work Notice received |
Jun 12, 2023 | Correspondence Received |
Aug 16, 2023 | Commencement of Work Notice received |
Oct 31, 2023 | Monitoring Report |
Apr 12, 2024 | Commencement of Work Notice received |