Action Date | Action Description |
---|---|
May 10, 2023 | Assent Application Received |
May 15, 2023 | Administrative Review for Completeness |
May 17, 2023 | Bio Team Review for Completeness |
May 17, 2023 | Deficient Application - Owner Notification Sent |
Jun 20, 2023 | Deficiency Response Received |
Jun 30, 2023 | Bio Team Review for Completeness |
Jul 06, 2023 | Application Accepted |
Jul 06, 2023 | Project Manager |
Jul 31, 2023 | HPHC Historical Preservation No Effect |
Aug 16, 2023 | Biologist Report |
Aug 18, 2023 | Typist for Processing |
Aug 18, 2023 | Executive Sign Off |
Aug 18, 2023 | Sent to Photo Copy |
Aug 18, 2023 | Permit Approved |
Aug 21, 2023 | Permit Mailed |
Aug 24, 2023 | Commencement of Work Notice received |