Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Land Evidence Date | |
Jul 06, 2023 | Assent Application Received |
Jul 11, 2023 | Administrative Review for Completeness |
Jul 19, 2023 | Bio Team Review for Completeness |
Jul 19, 2023 | Application Accepted |
Jul 19, 2023 | Project Manager |
Jul 31, 2023 | HPHC Historical Preservation No Effect |
Sep 22, 2023 | 30 day Public Notice Issued |
Oct 22, 2023 | Public Notice End Date |
Nov 07, 2023 | Correspondence Received |
Jan 31, 2024 | Plans Received |
Feb 09, 2024 | Dock/1.1.6 Review approval |
Feb 14, 2024 | Biologist Report |
Feb 16, 2024 | Typist for Processing |
Feb 16, 2024 | Executive Sign Off |
Feb 16, 2024 | Sent to Photo Copy |
Feb 16, 2024 | Permit Approved |
Feb 20, 2024 | Permit Mailed |
Feb 23, 2024 | Land Evidence Date |
Aug 19, 2024 | Modification Request |
Aug 22, 2024 | Administrative Review for Completeness |
Aug 28, 2024 | Bio Team Review for Completeness |
Aug 28, 2024 | Project Manager |
Aug 28, 2024 | Application Accepted |
Aug 29, 2024 | US Army Corps of Engineers Approval Received |
Sep 12, 2024 | 30 day Public Notice Issued |
Sep 18, 2024 | HPHC Historical Preservation No Effect |
Oct 12, 2024 | Public Notice End Date |
Oct 16, 2024 | Biologist Report |
Oct 21, 2024 | Typist for Processing |
Oct 21, 2024 | Modification Approved |
Oct 21, 2024 | Modification mailed |