Action Date | Action Description |
---|---|
Jul 12, 2023 | Assent Application Received |
Jul 17, 2023 | Administrative Review for Completeness |
Jul 19, 2023 | Bio Team Review for Completeness |
Jul 19, 2023 | Application Accepted |
Jul 19, 2023 | Project Manager |
Oct 03, 2023 | HPHC Historical Preservation No Effect |
Oct 23, 2023 | Correspondence Received |
Oct 23, 2023 | Correspondence Mailed/Faxed/E-mailed |
Oct 25, 2023 | Biologist Report |
Oct 26, 2023 | Typist for Processing |
Oct 26, 2023 | Executive Sign Off |
Oct 26, 2023 | Sent to Photo Copy |
Oct 26, 2023 | Permit Approved |
Nov 01, 2023 | Permit Mailed |
Oct 09, 2024 | Land Evidence Date |