Action Date | Action Description |
---|---|
Jul 12, 2023 | Assent Application Received |
Jul 17, 2023 | Administrative Review for Completeness |
Jul 21, 2023 | Bio Team Review for Completeness |
Jul 21, 2023 | Application Accepted |
Jul 21, 2023 | Project Manager |
Aug 10, 2023 | Plans Received |
Aug 25, 2023 | HPHC Historical Preservation No Effect |
Aug 25, 2023 | Biologist Report |
Aug 28, 2023 | Typist for Processing |
Aug 28, 2023 | Executive Sign Off |
Aug 28, 2023 | Sent to Photo Copy |
Aug 28, 2023 | Permit Approved |
Aug 29, 2023 | Permit Mailed |
Dec 06, 2023 | Modification Request |
Dec 08, 2023 | Administrative Review for Completeness |
Dec 08, 2023 | Bio Team Review for Completeness |
Dec 08, 2023 | Project Manager |
Dec 14, 2023 | Biologist Report |
Jan 05, 2024 | HPHC Historical Preservation No Effect |
Jan 08, 2024 | Typist for Processing |
Jan 08, 2024 | Executive Sign Off |
Jan 08, 2024 | Sent to Photo Copy |
Jan 08, 2024 | Modification Approved |
Jan 09, 2024 | Permit Mailed |