Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Jul 21, 2023 | Assent Application Received |
Jul 27, 2023 | Administrative Review for Completeness |
Aug 02, 2023 | Bio Team Review for Completeness |
Aug 02, 2023 | Application Accepted |
Aug 02, 2023 | Project Manager |
Aug 04, 2023 | HPHC Historical Preservation No Effect |
Aug 25, 2023 | 30 day Public Notice Issued |
Sep 25, 2023 | Public Notice End Date |
Sep 28, 2023 | Dock Meeting -- Approval |
Oct 03, 2023 | Biologist Report |
Oct 12, 2023 | Typist for Processing |
Oct 12, 2023 | Permit Approved |
Oct 13, 2023 | Permit Mailed |
Oct 13, 2023 | Executive Sign Off |
Oct 18, 2023 | Assent Correction Mailed |
Nov 06, 2023 | Land Evidence Date |