Action Date | Action Description |
---|---|
Land Evidence Date | |
Sep 01, 2023 | Maintenance Certification Request |
Sep 08, 2023 | Administrative Review for Completeness |
Sep 13, 2023 | Eng Team Review for Completeness |
Sep 13, 2023 | Deficient Application - Owner Notification Sent |
Sep 28, 2023 | Deficiency Response Received |
Oct 12, 2023 | Eng Team Review for Completeness |
Oct 12, 2023 | Application Accepted |
Oct 12, 2023 | Project Manager |
Oct 19, 2023 | HPHC Historical Preservation No Effect |
Oct 19, 2023 | Plans Received |
Oct 25, 2023 | Engineering Report |
Oct 31, 2023 | Typist for Processing |
Oct 31, 2023 | Executive Sign Off |
Oct 31, 2023 | Sent to Photo Copy |
Oct 31, 2023 | Permit Approved |
Nov 02, 2023 | Permit Mailed |