Oct 10, 2023 | Assent Application Received |
Oct 16, 2023 | Administrative Review for Completeness |
Nov 03, 2023 | Bio Team Review for Completeness |
Nov 03, 2023 | Deficient Application - Owner Notification Sent |
Nov 17, 2023 | Deficiency Response Received |
Nov 22, 2023 | Bio Team Review for Completeness |
Nov 22, 2023 | Application Accepted |
Nov 22, 2023 | Project Manager |
Nov 28, 2023 | Biologist Report |
Nov 28, 2023 | Additional Information Received |
Dec 01, 2023 | HPHC Historical Preservation No Effect |
Dec 05, 2023 | Typist for Processing |
Dec 05, 2023 | Executive Sign Off |
Dec 05, 2023 | Sent to Photo Copy |
Dec 05, 2023 | Permit Approved |
Dec 06, 2023 | Permit Mailed |
Dec 19, 2023 | Land Evidence Date |
Mar 14, 2024 | Commencement of Work Notice received |