Action Date | Action Description |
---|---|
Land Evidence Date | |
Oct 10, 2023 | Maintenance Certification Request |
Oct 20, 2023 | Administrative Review for Completeness |
Oct 24, 2023 | Bio Team Review for Completeness |
Oct 24, 2023 | Deficient Application - Owner Notification Sent |
Nov 30, 2023 | Deficiency Response Received |
Dec 06, 2023 | Bio Team Review for Completeness |
Dec 06, 2023 | Application Accepted |
Dec 06, 2023 | Project Manager |
Jan 05, 2024 | HPHC Historical Preservation No Effect |
Jan 08, 2024 | Biologist Report |
Jan 09, 2024 | Typist for Processing |
Jan 09, 2024 | Executive Sign Off |
Jan 09, 2024 | Sent to Photo Copy |
Jan 09, 2024 | Permit Approved |
Jan 11, 2024 | Permit Mailed |