Action Date | Action Description |
---|---|
Feb 06, 2024 | Freshwater Wetlands Application - New - received |
Feb 06, 2024 | Administrative Review for Completeness |
Feb 09, 2024 | Additional Information Received |
Mar 27, 2024 | Application Accepted |
Mar 27, 2024 | Bio Team Review for Completeness |
Mar 27, 2024 | Project Manager |
Apr 03, 2024 | Biologist Report |
Apr 03, 2024 | Typist for Processing |
Apr 03, 2024 | Permit Approved |
Apr 04, 2024 | Permit Mailed |
Apr 04, 2024 | Executive Sign Off |
Apr 05, 2024 | HPHC Historical Preservation No Effect |