Action Date | Action Description |
---|---|
Feb 22, 2024 | Assent Application Received |
Feb 27, 2024 | Administrative Review for Completeness |
Mar 13, 2024 | Eng Team Review for Completeness |
Mar 13, 2024 | Bio Team Review for Completeness |
Mar 13, 2024 | Project Manager |
Mar 13, 2024 | Application Accepted |
Apr 12, 2024 | HPHC Historical Preservation No Effect |
Apr 30, 2024 | 30 day Public Notice Issued |
May 29, 2024 | Biologist Report |
May 29, 2024 | Engineering Report |
May 30, 2024 | Public Notice End Date |
Jun 10, 2024 | Typist for Processing |
Jun 10, 2024 | Executive Sign Off |
Jun 10, 2024 | Sent to Photo Copy |
Jun 10, 2024 | Permit Approved |
Jun 12, 2024 | Permit Mailed |
Jun 24, 2024 | Land Evidence Date |