Action Date | Action Description |
---|---|
Mar 20, 2024 | Assent Application Received |
Mar 26, 2024 | Administrative Review for Completeness |
Mar 29, 2024 | Eng Team Review for Completeness |
Mar 29, 2024 | Application Accepted |
Mar 29, 2024 | Project Manager |
Apr 05, 2024 | HPHC Historical Preservation No Effect |
Apr 19, 2024 | Typist for Processing |
Apr 19, 2024 | Executive Sign Off |
Apr 19, 2024 | Sent to Photo Copy |
Apr 19, 2024 | Permit Approved |
Apr 19, 2024 | Engineering Report |
Apr 23, 2024 | Permit Mailed |