Action Date | Action Description |
---|---|
May 15, 2024 | Maintenance Certification Request |
May 20, 2024 | Administrative Review for Completeness |
Jun 25, 2024 | Plans Received |
Jul 26, 2024 | Application Accepted |
Jul 26, 2024 | Project Manager |
Jul 26, 2024 | Eng Team Review for Completeness |
Aug 16, 2024 | Engineering Report |
Aug 16, 2024 | HPHC Historical Preservation No Effect |
Aug 19, 2024 | Typist for Processing |
Aug 19, 2024 | Executive Sign Off |
Aug 19, 2024 | Sent to Photo Copy |
Aug 19, 2024 | Permit Approved |
Aug 20, 2024 | Permit Mailed |
Aug 27, 2024 | Land Evidence Date |
Sep 16, 2024 | Commencement of Work Notice received |