Action Date | Action Description |
---|---|
Jun 06, 2024 | Assent Application Received |
Jun 12, 2024 | Administrative Review for Completeness |
Jun 14, 2024 | Bio Team Review for Completeness |
Jun 24, 2024 | Deficient Application - Owner Notification Sent |
Jul 16, 2024 | Deficiency Response Received |
Jul 16, 2024 | Eng Team Review for Completeness |
Jul 16, 2024 | Application Accepted |
Jul 16, 2024 | Project Manager |
Jul 25, 2024 | Engineering Report |
Jul 26, 2024 | Finding Of No Significant Impact (FONSI) |
Jul 29, 2024 | Permit Mailed |
Aug 07, 2024 | HPHC Historical Preservation No Effect |