Action Date | Action Description |
---|---|
Jun 17, 2024 | Maintenance Certification Request |
Jun 24, 2024 | Administrative Review for Completeness |
Jun 25, 2024 | Bio Team Review for Completeness |
Jul 25, 2024 | Additional Information Requested from Applicant |
Aug 19, 2024 | Additional Information Requested from Applicant |
Aug 20, 2024 | Additional Information Received |
Aug 21, 2024 | Application Accepted |
Aug 21, 2024 | Project Manager |
Aug 21, 2024 | Bio Team Review for Completeness |
Aug 21, 2024 | Additional Information Requested from Applicant |
Sep 13, 2024 | HPHC Historical Preservation No Effect |
Sep 18, 2024 | Correspondence Received |
Sep 25, 2024 | Additional Information Received |
Oct 11, 2024 | Typist for Processing |
Oct 11, 2024 | Executive Sign Off |
Oct 11, 2024 | Sent to Photo Copy |
Oct 11, 2024 | Permit Approved |
Oct 11, 2024 | Biologist Report |
Oct 15, 2024 | Permit Mailed |
Oct 23, 2024 | Land Evidence Date |
Nov 01, 2024 | Commencement of Work Notice received |