Action Date | Action Description |
---|---|
Land Evidence Date | |
Aug 07, 2024 | Assent Application Received |
Aug 13, 2024 | Administrative Review for Completeness |
Aug 15, 2024 | Bio Team Review for Completeness |
Aug 15, 2024 | Project Manager |
Aug 15, 2024 | Application Accepted |
Aug 30, 2024 | HPHC Historical Preservation No Effect |
Sep 19, 2024 | Additional Information Received |
Sep 24, 2024 | Biologist Report |
Oct 01, 2024 | Typist for Processing |
Oct 01, 2024 | Executive Sign Off |
Oct 01, 2024 | Sent to Photo Copy |
Oct 01, 2024 | Permit Approved |
Oct 04, 2024 | Permit Mailed |