Action Date |
Action Description |
Feb 25, 2003 |
Application Accepted |
Feb 27, 2003 |
Biologist Report |
Feb 27, 2003 |
Engineering Report |
Feb 27, 2003 |
Permit Approved |
Apr 12, 2004 |
Correspondence Received |
Oct 01, 2004 |
Land Evidence Date |
Jul 15, 2005 |
ISDS Approved |
Nov 28, 2005 |
Extension of Permit Request |
Dec 09, 2005 |
Process Extension |
Dec 09, 2005 |
Typist for Processing |
Dec 09, 2005 |
Extension Approved |
Dec 12, 2005 |
Executive Sign Off |
Dec 12, 2005 |
Sent to Photo Copy |
Jan 13, 2006 |
Correspondence Mailed/Faxed/E-mailed |
Jul 10, 2006 |
Correspondence Received |
Sep 21, 2006 |
Correspondence Received |
Dec 22, 2006 |
Extension of Permit Request |
Jan 03, 2007 |
Extension Approved |
Sep 07, 2007 |
Correspondence Mailed/Faxed/E-mailed |
Jan 14, 2008 |
Extension of Permit Request |
Mar 31, 2008 |
Extension Approved |
May 12, 2008 |
Commencement of Work Notice received |
Jan 02, 2009 |
Extension of Permit Request |
Jul 13, 2009 |
Ready to Schedule Semi-Monthly Meeting |
Jul 20, 2009 |
Mail Agenda Notice |
Jul 28, 2009 |
Phone Call |
Jul 28, 2009 |
Extension Approved |
Jul 28, 2009 |
Semi-Monthly Meeting Held |
Jul 28, 2009 |
Semi-Monthly Meeting Date Scheduled |
Jul 22, 2010 |
Correspondence Received |
Jul 23, 2010 |
Extension Correction Mailed |
Apr 07, 2011 |
Correspondence Received |
Dec 19, 2011 |
Extension Toll letter mailed |
May 08, 2013 |
Correspondence Received |
May 13, 2013 |
Modification Request |
May 13, 2013 |
Modification Request |
May 14, 2013 |
Administrative Review for Completeness |
May 14, 2013 |
Team Review for Completeness |
May 14, 2013 |
Administrative Review for Completeness |
May 24, 2013 |
Plans Received |
Jun 03, 2013 |
Typist for Processing |
Jun 03, 2013 |
Modification Approved |
Jun 03, 2013 |
Modification Approved |
Jun 03, 2013 |
Pre-construction requirement by CRMC staff |
Jun 03, 2013 |
Pre-construction requirement by CRMC staff |
Jun 03, 2013 |
Biologist Report |
Jun 03, 2013 |
Biologist Report |
Jun 04, 2013 |
Executive Sign Off |
Jun 04, 2013 |
Sent to Photo Copy |
Jun 10, 2013 |
HPHC Historical Preservation No Effect |
Jun 10, 2013 |
HPHC Historical Preservation No Effect |
Jul 02, 2013 |
Land Evidence Date |
Jul 02, 2013 |
Land Evidence Date |
Sep 24, 2013 |
Modification Request |
Sep 27, 2013 |
Administrative Review for Completeness |
Oct 01, 2013 |
Team Review for Completeness |
Oct 09, 2013 |
Biologist Report |
Oct 09, 2013 |
Typist for Processing |
Oct 09, 2013 |
HPHC Historical Preservation No Effect |
Oct 10, 2013 |
Executive Sign Off |
Oct 10, 2013 |
Sent to Photo Copy |
Oct 10, 2013 |
Modification Approved |
Nov 07, 2013 |
Land Evidence Date |
Apr 28, 2014 |
Correspondence Mailed/Faxed/E-mailed |
Jul 15, 2015 |
Commencement of Work Notice received |
Nov 13, 2015 |
Duplicate Original Assent requested/mailed |
Feb 11, 2016 |
Modification Request |
Feb 12, 2016 |
Administrative Review for Completeness |
Feb 15, 2016 |
Team Review for Completeness |
Feb 16, 2016 |
Biologist Report |
Feb 17, 2016 |
Typist for Processing |
Feb 18, 2016 |
Executive Sign Off |
Feb 18, 2016 |
Sent to Photo Copy |
Feb 18, 2016 |
Modification Approved |
Feb 25, 2016 |
HPHC Historical Preservation No Effect |
Apr 14, 2016 |
Land Evidence Date |