Action Date | Action Description |
---|---|
Jul 26, 2004 | Application Accepted |
Jul 26, 2004 | 30 day Public Notice Issued |
Aug 16, 2004 | Historical Preservation Approval Granted |
Aug 26, 2004 | Category B assigned |
Aug 26, 2004 | Engineering Report |
Oct 10, 2004 | Biologist Report |
Oct 12, 2004 | Meeting Held |
Oct 26, 2004 | Permit Approved |
Oct 26, 2004 | Land Evidence Date |
Nov 03, 2004 | 30 Day Appeal Notification to Owner |
Nov 09, 2004 | Council Approval Granted |
Jan 11, 2005 | Extension of Permit Request |
Jan 11, 2005 | Ready to Schedule Semi-Monthly Meeting |
Jan 18, 2005 | Mail Agenda Notice |
Jan 25, 2005 | Semi-Monthly Meeting Held |
Jan 25, 2005 | Semi-Monthly Meeting Date Scheduled |
Jan 25, 2005 | Council Approval - Extension Granted |
Feb 02, 2005 | Extension Approved |
Feb 02, 2005 | Typist for Processing |
Feb 02, 2005 | Executive Sign Off |
Feb 02, 2005 | Sent to Photo Copy |
Nov 08, 2005 | Correspondence Received |
Nov 29, 2005 | Correspondence Mailed/Faxed/E-mailed |
Jan 03, 2006 | Correspondence Received |
Jul 28, 2008 | Extension of Permit Request |
Nov 12, 2008 | Correspondence Received |
Nov 17, 2008 | Extension Approved |
Nov 17, 2008 | Enforcement Compliance Inspection Required |
Aug 26, 2009 | Extension of Permit Request |
Oct 13, 2009 | Enforcement Compliance Inspection Required |
Oct 23, 2009 | Process Extension |
Oct 23, 2009 | Extension Approved |
Sep 17, 2012 | Modification Request |
Sep 18, 2012 | Administrative Review for Completeness |
Sep 26, 2012 | Team Review for Completeness |
Sep 26, 2012 | Engineering Report |
Sep 26, 2012 | Typist for Processing |
Sep 26, 2012 | Modification Approved |
Sep 28, 2012 | Executive Sign Off |
Sep 28, 2012 | Sent to Photo Copy |
Jul 01, 2014 | Extension Toll letter mailed |
Nov 12, 2015 | Extension Toll letter mailed |
Jul 21, 2017 | Correspondence Mailed/Faxed/E-mailed |