Action Date | Action Description |
---|---|
Feb 03, 2005 | Assent Application Received |
Feb 04, 2005 | Administrative Review for Completeness |
Feb 08, 2005 | Deficient Application - Owner Notification Sent |
Feb 09, 2005 | Correspondence Received |
Feb 16, 2005 | Deficiency Response Received |
Feb 17, 2005 | Team Review for Completeness |
Feb 17, 2005 | Application Accepted |
Mar 01, 2005 | HPHC Review Pending |
May 10, 2005 | 30 day Public Notice Issued |
Jun 10, 2005 | Public Notice End Date |
Jun 10, 2005 | Objections/Comments Received |
Jun 10, 2005 | Correspondence Received |
Jul 20, 2005 | Correspondence Received |
Aug 22, 2005 | Correspondence Received |
Feb 08, 2006 | Objections/Comments Received |
Apr 25, 2006 | Correspondence Mailed/Faxed/E-mailed |
Mar 16, 2009 | 30-Day Notification of Cancellation letter |
Apr 02, 2009 | Additional Information Received |
May 11, 2009 | Correspondence Received |
Jun 16, 2009 | Typist for Processing |
Jun 16, 2009 | Executive Sign Off |
Jun 16, 2009 | Biologist Report |
Jun 16, 2009 | Engineering Report |
Jun 16, 2009 | Permit Approved |
Jun 18, 2009 | Sent to Photo Copy |
Jul 02, 2009 | Assent Correction Request Received |
Jul 02, 2009 | Assent Correction Mailed |
Jul 31, 2009 | Commencement of Work Notice received |
Jul 31, 2009 | Land Evidence Date |
Jul 13, 2011 | Extension Toll letter mailed |