Action Date | Action Description |
---|---|
Apr 13, 2005 | Assent Application Received |
Apr 14, 2005 | Administrative Review for Completeness |
Apr 14, 2005 | Application Accepted |
May 05, 2005 | Deficient Application - Owner Notification Sent |
May 16, 2005 | Deficient Application Picked Up |
Jul 13, 2005 | Deficiency Response Received |
Jul 20, 2005 | Team Review for Completeness |
Jul 28, 2005 | Biologist Report |
Jul 28, 2005 | Engineering Report |
Jul 28, 2005 | Plans Received |
Jul 28, 2005 | Typist for Processing |
Jul 28, 2005 | Executive Sign Off |
Jul 28, 2005 | Sent to Photo Copy |
Jul 28, 2005 | Permit Approved |
Aug 01, 2005 | Historical Preservation Approval Granted |
Aug 03, 2005 | Land Evidence Date |
Aug 12, 2005 | Historical Preservation Approval Granted |
Apr 18, 2006 | Correspondence Mailed/Faxed/E-mailed |