Action Date | Action Description |
---|---|
May 25, 2005 | Assent Application Received |
May 26, 2005 | Administrative Review for Completeness |
Jun 06, 2005 | Deficient Application - Owner Notification Sent |
Jun 13, 2005 | Deficient Application Picked Up |
Jun 16, 2005 | Deficiency Response Received |
Jun 17, 2005 | Team Review for Completeness |
Jun 20, 2005 | Application Accepted |
Jul 14, 2005 | HPHC Review Pending |
Jul 25, 2005 | Engineering Report |
Aug 02, 2005 | Typist for Processing |
Aug 02, 2005 | Executive Sign Off |
Aug 02, 2005 | Sent to Photo Copy |
Aug 02, 2005 | Permit Approved |