Action Date | Action Description |
---|---|
Jul 29, 2005 | Assent Application Received |
Aug 01, 2005 | Administrative Review for Completeness |
Aug 04, 2005 | Team Review for Completeness |
Aug 04, 2005 | Application Accepted |
Aug 25, 2005 | HPHC Review Pending |
Aug 25, 2005 | Historical Preservation Approval Granted |
Oct 25, 2005 | Biologist Report |
Oct 25, 2005 | Engineering Report |
Oct 26, 2005 | Typist for Processing |
Oct 26, 2005 | Executive Sign Off |
Oct 26, 2005 | Sent to Photo Copy |
Oct 26, 2005 | Permit Approved |
Nov 03, 2005 | Land Evidence Date |
Nov 14, 2005 | Commencement of Work Notice received |
Dec 16, 2005 | Modification Request |
Dec 19, 2005 | Administrative Review for Completeness |
Dec 23, 2005 | Team Review for Completeness |
Jan 18, 2006 | HPHC Historical Preservation No Effect |
Mar 08, 2006 | Typist for Processing |
Mar 08, 2006 | Executive Sign Off |
Mar 08, 2006 | Sent to Photo Copy |
Mar 08, 2006 | Biologist Report |
Mar 08, 2006 | Engineering Report |
Mar 09, 2006 | Additional Information Received |
Mar 13, 2006 | Modification Approved |
Mar 20, 2006 | Land Evidence Date |