Action Date | Action Description |
---|---|
Aug 05, 2005 | Assent Application Received |
Aug 08, 2005 | Administrative Review for Completeness |
Aug 12, 2005 | Deficient Application - Owner Notification Sent |
Sep 07, 2005 | Phone Call |
Sep 08, 2005 | Deficiency Response Received |
Sep 09, 2005 | Team Review for Completeness |
Sep 09, 2005 | Application Accepted |
Sep 14, 2005 | Biologist Report |
Sep 14, 2005 | Engineering Report |
Sep 15, 2005 | Typist for Processing |
Sep 15, 2005 | Executive Sign Off |
Sep 15, 2005 | Sent to Photo Copy |
Sep 30, 2005 | Permit Approved |
Sep 30, 2005 | HPHC Review Pending |
Oct 26, 2005 | Land Evidence Date |
Mar 12, 2007 | Modification Request |
Mar 12, 2007 | Administrative Review for Completeness |
Mar 28, 2007 | Team Review for Completeness |
Mar 28, 2007 | Team Review for Completeness |
Mar 29, 2007 | Biologist Report |
Mar 29, 2007 | Engineering Report |
Mar 29, 2007 | Typist for Processing |
Mar 29, 2007 | Executive Sign Off |
Mar 29, 2007 | Sent to Photo Copy |
Mar 29, 2007 | Modification Approved |
Jun 20, 2007 | Land Evidence Date |
Jul 09, 2008 | Extension of Permit Request |
Dec 05, 2008 | Enforcement Compliance Inspection Required |
Dec 09, 2008 | Extension Approved |