Action Date | Action Description |
---|---|
Nov 21, 2005 | Assent Application Received |
Nov 22, 2005 | Administrative Review for Completeness |
Nov 22, 2005 | Team Review for Completeness |
Nov 22, 2005 | Application Accepted |
Nov 22, 2005 | Category A* (Docks) |
Dec 06, 2005 | HPHC Historical Preservation No Effect |
Aug 21, 2006 | 30 day Public Notice Issued |
Sep 18, 2006 | US Army Corp of Engineers Permit Date |
Sep 21, 2006 | Public Notice End Date |
Sep 25, 2006 | US Army Corps of Engineers Approval Received |
Sep 29, 2006 | Dock Meeting Scheduled (Admin) |
Sep 29, 2006 | Biologist Report |
Sep 29, 2006 | Engineering Report |
Sep 29, 2006 | Land Evidence Date |
Sep 29, 2006 | Dock sub-committee Approved |
Oct 02, 2006 | Typist for Processing |
Oct 03, 2006 | Executive Sign Off |
Oct 03, 2006 | Sent to Photo Copy |
Oct 03, 2006 | Permit Approved |
Jan 02, 2007 | Land Evidence Date |
Jun 21, 2007 | Commencement of Work Notice received |
Aug 25, 2008 | Modification Request |
Aug 28, 2008 | Administrative Review for Completeness |
Aug 28, 2008 | Team Review for Completeness |
Aug 28, 2008 | Team Review for Completeness |
Sep 12, 2008 | HPHC Historical Preservation No Effect |
Sep 18, 2008 | 30 day Public Notice Issued |
Oct 14, 2008 | US Army Corp of Engineers Permit Date |
Oct 14, 2008 | US Army Corps of Engineers Approval Received |
Oct 14, 2008 | US Army Corp of Engineers Permit Date |
Oct 14, 2008 | US Army Corps of Engineers Approval Received |
Oct 18, 2008 | Public Notice End Date |
Nov 03, 2008 | Dock Meeting -- Approval |
Nov 05, 2008 | Modification Approved |
Nov 05, 2008 | Typist for Processing |
Nov 05, 2008 | Executive Sign Off |
Nov 05, 2008 | Sent to Photo Copy |
Nov 05, 2008 | Biologist Report |
Nov 05, 2008 | Engineering Report |
Dec 17, 2008 | Land Evidence Date |