Action Date | Action Description |
---|---|
Dec 16, 2005 | Assent Application Received |
Dec 16, 2005 | Administrative Review for Completeness |
Jan 10, 2006 | Deficient Application - Owner Notification Sent |
Mar 01, 2006 | Deficiency Response Received |
Mar 07, 2006 | Deficient Application - Owner Notification Sent |
Mar 07, 2006 | Deficient Application Picked Up |
Apr 13, 2006 | Deficiency Response Received |
Apr 13, 2006 | Administrative Review for Completeness |
Apr 21, 2006 | Team Review for Completeness |
Apr 21, 2006 | Application Accepted |
Apr 21, 2006 | Category A* (Docks) |
May 01, 2006 | HPHC Historical Preservation No Effect |
May 04, 2006 | 30 day Public Notice Issued |
May 10, 2006 | Plans Received |
May 11, 2006 | Correspondence Received |
May 12, 2006 | Objections/Comments Received |
May 22, 2006 | Plans Received |
Jun 04, 2006 | Public Notice End Date |
Aug 08, 2006 | US Army Corp of Engineers Permit Date |
Aug 11, 2006 | US Army Corps of Engineers Approval Received |
Aug 21, 2006 | Correspondence Received |
Aug 25, 2006 | Dock Meeting Scheduled (Admin) |
Aug 29, 2006 | Typist for Processing |
Aug 29, 2006 | Executive Sign Off |
Aug 29, 2006 | Sent to Photo Copy |
Aug 29, 2006 | Biologist Report |
Aug 29, 2006 | Engineering Report |
Aug 31, 2006 | Permit Approved |
Sep 05, 2006 | Land Evidence Date |