Action Date | Action Description |
---|---|
Dec 20, 2006 | Assent Application Received |
Dec 21, 2006 | Administrative Review for Completeness |
Dec 21, 2006 | Team Review for Completeness |
Dec 21, 2006 | Team Review for Completeness |
Dec 21, 2006 | Application Accepted |
Dec 21, 2006 | Category A* (Docks) |
Jan 08, 2007 | 30 day Public Notice Issued |
Jan 17, 2007 | HPHC Historical Preservation No Effect |
Feb 08, 2007 | Public Notice End Date |
Feb 27, 2007 | Plans Received |
Feb 28, 2007 | Typist for Processing |
Feb 28, 2007 | Executive Sign Off |
Feb 28, 2007 | Sent to Photo Copy |
Feb 28, 2007 | Biologist Report |
Feb 28, 2007 | Engineering Report |
Feb 28, 2007 | Permit Approved |
Mar 12, 2007 | US Army Corp of Engineers Permit Date |
Mar 14, 2007 | US Army Corps of Engineers Approval Received |
Mar 30, 2007 | Land Evidence Date |