Action Date | Action Description |
---|---|
Apr 20, 2007 | Assent Application Received |
Apr 23, 2007 | Administrative Review for Completeness |
May 01, 2007 | Team Review for Completeness |
May 01, 2007 | Application Accepted |
May 02, 2007 | Additional Information Requested from Applicant |
May 11, 2007 | Engineering Report |
May 14, 2007 | Typist for Processing |
May 14, 2007 | Executive Sign Off |
May 14, 2007 | Sent to Photo Copy |
May 14, 2007 | Permit Approved |
May 15, 2007 | HPHC Historical Preservation No Effect |
May 25, 2007 | Land Evidence Date |