Action Date | Action Description |
---|---|
May 04, 2007 | Assent Application Received |
May 07, 2007 | Administrative Review for Completeness |
May 07, 2007 | Team Review for Completeness |
May 07, 2007 | Deficiency - Phone Call to Applicant/Owner |
May 08, 2007 | Application Accepted |
May 08, 2007 | Team Review for Completeness |
May 08, 2007 | Category A* (Docks) |
May 17, 2007 | HPHC Historical Preservation No Effect |
Jun 11, 2007 | Additional Information Received |
Jun 11, 2007 | 30 day Public Notice Issued |
Jul 11, 2007 | Public Notice End Date |
Jul 17, 2007 | US Army Corp of Engineers Permit Date |
Jul 19, 2007 | US Army Corps of Engineers Approval Received |
Jul 24, 2007 | Dock Meeting -- Approval |
Jul 25, 2007 | Permit Approved |
Jul 25, 2007 | Typist for Processing |
Jul 25, 2007 | Executive Sign Off |
Jul 25, 2007 | Sent to Photo Copy |
Jul 25, 2007 | Biologist Report |
Jul 25, 2007 | Engineering Report |
Dec 21, 2007 | Land Evidence Date |
Jul 23, 2010 | Commencement of Work Notice received |