Action Date | Action Description |
---|---|
Monitoring Report | |
Jun 19, 2007 | Assent Application Received |
Jun 20, 2007 | Administrative Review for Completeness |
Jun 20, 2007 | Team Review for Completeness |
Jun 20, 2007 | Team Review for Completeness |
Jun 20, 2007 | Application Accepted |
Jul 09, 2007 | HPHC Historical Preservation No Effect |
Aug 07, 2007 | 30 day Public Notice Issued |
Aug 07, 2007 | Public Hearing Notices Mailed |
Sep 05, 2007 | Correspondence Received |
Sep 11, 2007 | Special Exception Scheduled for Semi-Monthly |
Sep 12, 2007 | Correspondence Received |
Sep 14, 2007 | Biologist Report |
Sep 14, 2007 | Engineering Report |
Sep 14, 2007 | Plans Received |
Sep 17, 2007 | Public Notice End Date |
Sep 18, 2007 | Executive Signoff of Staff Reports |
Sep 25, 2007 | Council Approval Granted |
Sep 25, 2007 | Semi-Monthly Meeting Held |
Sep 25, 2007 | Special Exception Scheduled for Semi-Monthly |
Sep 25, 2007 | Semi-Monthly Meeting Date Scheduled |
Oct 18, 2007 | Land Evidence Date |
Oct 18, 2007 | Legal Response/Decision |
Oct 24, 2007 | Typist for Processing |
Oct 24, 2007 | Executive Sign Off |
Oct 24, 2007 | Sent to Photo Copy |
Oct 24, 2007 | Permit Approved |
Oct 24, 2007 | Stipulation Package from Biologist |
Oct 24, 2007 | Stipulation Package by Engineer |
Nov 01, 2007 | Land Evidence Date |
Nov 01, 2007 | US Army Corp of Engineers Permit Date |
Nov 07, 2007 | US Army Corps of Engineers Approval Received |
Aug 28, 2008 | Commencement of Work Notice received |
Aug 28, 2008 | Monitoring Report |
Oct 14, 2008 | Monitoring Report |
Nov 20, 2008 | Monitoring Report |
Nov 21, 2008 | Commencement of Work Notice received |
Dec 10, 2008 | Monitoring Report |
Jan 05, 2009 | Water Quality Certification |
Feb 13, 2009 | Monitoring Report |
Mar 18, 2009 | Monitoring Report |
Jul 07, 2009 | Monitoring Report |
Jul 20, 2010 | Monitoring Report |