Action Date | Action Description |
---|---|
Jun 29, 2007 | Assent Application Received |
Jul 02, 2007 | Administrative Review for Completeness |
Jul 13, 2007 | Team Review for Completeness |
Jul 13, 2007 | Team Review for Completeness |
Jul 13, 2007 | Deficient Application - Owner Notification Sent |
Sep 27, 2007 | Deficient Application Discarded/No deficiency Reponse |
Nov 08, 2007 | Deficiency Response Received |
Nov 09, 2007 | Administrative Review for Completeness |
Nov 15, 2007 | Team Review for Completeness |
Nov 15, 2007 | Team Review for Completeness |
Nov 15, 2007 | Application Accepted |
Nov 15, 2007 | Category A* (Docks) |
Nov 20, 2007 | Plans Received |
Nov 24, 2007 | HPHC Historical Preservation No Effect |
Jan 16, 2008 | 30 day Public Notice Issued |
Feb 16, 2008 | Public Notice End Date |
Mar 14, 2008 | Dock Meeting -- Approval |
Mar 24, 2008 | Plans Received |
Apr 08, 2008 | Biologist Report |
Apr 08, 2008 | Engineering Report |
Apr 09, 2008 | Typist for Processing |
Apr 09, 2008 | Executive Sign Off |
Apr 09, 2008 | Sent to Photo Copy |
Apr 09, 2008 | Permit Approved |
Apr 21, 2008 | Land Evidence Date |
May 05, 2008 | US Army Corp of Engineers Permit Date |
May 08, 2008 | US Army Corps of Engineers Approval Received |