Action Date | Action Description |
---|---|
Jul 17, 2007 | Assent Application Received |
Jul 18, 2007 | Administrative Review for Completeness |
Sep 07, 2007 | Team Review for Completeness |
Sep 07, 2007 | Application Accepted |
Oct 01, 2007 | Additional Information Requested from Applicant |
Oct 01, 2007 | 30-Day Notification of Cancellation letter |
Oct 15, 2007 | Plans Received |
Nov 20, 2007 | Biologist Report |
Nov 21, 2007 | Typist for Processing |
Nov 21, 2007 | Executive Sign Off |
Nov 21, 2007 | Sent to Photo Copy |
Nov 21, 2007 | Permit Approved |
Nov 26, 2007 | Land Evidence Date |
Jun 28, 2022 | Modification Request |
Jul 05, 2022 | Administrative Review for Completeness |
Jul 06, 2022 | Bio Team Review for Completeness |
Jul 07, 2022 | Project Manager |
Jul 22, 2022 | HPHC Review Pending |
Jul 22, 2022 | HPHC Historical Preservation No Effect |
Aug 17, 2022 | Additional Information Requested from Applicant |
Aug 19, 2022 | Additional Information Received |
Sep 08, 2022 | Biologist Report |
Sep 09, 2022 | Typist for Processing |
Sep 09, 2022 | Executive Sign Off |
Sep 09, 2022 | Sent to Photo Copy |
Sep 09, 2022 | Modification Approved |
Jan 11, 2023 | Land Evidence Date |