Action Date | Action Description |
---|---|
Jul 19, 2007 | Assent Application Received |
Jul 23, 2007 | Administrative Review for Completeness |
Jul 26, 2007 | Team Review for Completeness |
Jul 26, 2007 | Team Review for Completeness |
Jul 26, 2007 | Application Accepted |
Jul 26, 2007 | Category A* (Docks) |
Aug 03, 2007 | HPHC Historical Preservation No Effect |
Aug 06, 2007 | 30 day Public Notice Issued |
Sep 06, 2007 | Public Notice End Date |
Sep 13, 2007 | Dock Meeting -- Approval |
Sep 17, 2007 | US Army Corp of Engineers Permit Date |
Sep 18, 2007 | Typist for Processing |
Sep 18, 2007 | Executive Sign Off |
Sep 18, 2007 | Sent to Photo Copy |
Sep 18, 2007 | Biologist Report |
Sep 18, 2007 | Engineering Report |
Sep 18, 2007 | Permit Approved |
Sep 19, 2007 | US Army Corps of Engineers Approval Received |
Sep 27, 2007 | Land Evidence Date |
May 01, 2008 | Commencement of Work Notice received |
Jun 13, 2013 | Correspondence Received |
Jun 13, 2013 | Site Inspection |
Jun 13, 2013 | Site Inspection |
Dec 17, 2018 | Correspondence Received |