Action Date | Action Description |
---|---|
Jul 25, 2007 | Assent Application Received |
Jul 26, 2007 | Administrative Review for Completeness |
Aug 02, 2007 | Team Review for Completeness |
Aug 02, 2007 | Team Review for Completeness |
Aug 02, 2007 | Application Accepted |
Sep 04, 2007 | HPHC Historical Preservation No Effect |
Oct 01, 2007 | Typist for Processing |
Oct 01, 2007 | Executive Sign Off |
Oct 01, 2007 | Sent to Photo Copy |
Oct 01, 2007 | Permit Approved |
Oct 01, 2007 | Biologist Report |
Oct 01, 2007 | Engineering Report |
Dec 12, 2007 | Land Evidence Date |