Action Date | Action Description |
---|---|
Aug 29, 2007 | Assent Application Received |
Aug 30, 2007 | Administrative Review for Completeness |
Aug 30, 2007 | Team Review for Completeness |
Aug 30, 2007 | Team Review for Completeness |
Aug 30, 2007 | Application Accepted |
Aug 30, 2007 | Category A* (Docks) |
Aug 30, 2007 | 30 day Public Notice Issued |
Sep 13, 2007 | HPHC Historical Preservation No Effect |
Sep 30, 2007 | Public Notice End Date |
Nov 20, 2007 | Dock Meeting Scheduled (Admin) |
Mar 03, 2008 | Plans Received |
Mar 19, 2008 | Typist for Processing |
Mar 19, 2008 | Executive Sign Off |
Mar 19, 2008 | Sent to Photo Copy |
Mar 19, 2008 | Permit Approved |
Mar 19, 2008 | Biologist Report |
Mar 19, 2008 | Engineering Report |
Mar 25, 2008 | US Army Corp of Engineers Permit Date |
Mar 27, 2008 | US Army Corps of Engineers Approval Received |
Jul 24, 2008 | Land Evidence Date |
Jan 10, 2011 | Extension of Permit Request |
Feb 28, 2011 | Extension Toll letter mailed |
Dec 19, 2011 | Note to File |
Jan 10, 2012 | Extension Toll letter mailed |