Action Date |
Action Description |
Sep 17, 2007 |
Assent Application Received |
Sep 17, 2007 |
Administrative Review for Completeness |
Oct 03, 2007 |
Team Review for Completeness |
Oct 03, 2007 |
Deficient Application - Owner Notification Sent |
Oct 15, 2007 |
Deficiency Response Received |
Nov 14, 2007 |
Deficiency Response Received |
Nov 15, 2007 |
Administrative Review for Completeness |
Nov 19, 2007 |
Team Review for Completeness |
Nov 19, 2007 |
Deficient Application - Owner Notification Sent |
Dec 14, 2007 |
Deficiency Response Received |
Dec 24, 2007 |
Administrative Review for Completeness |
Dec 24, 2007 |
Team Review for Completeness |
Dec 24, 2007 |
Application Accepted |
Dec 28, 2007 |
Category A* (Docks) |
Jan 07, 2008 |
HPHC Historical Preservation No Effect |
Jan 31, 2008 |
Additional Information Received |
Apr 04, 2008 |
30 day Public Notice Issued |
Apr 15, 2008 |
Correspondence Received |
May 04, 2008 |
Public Notice End Date |
May 06, 2008 |
Objections/Comments Received |
Jun 25, 2008 |
US Army Corp of Engineers Permit Date |
Jun 27, 2008 |
US Army Corps of Engineers Approval Received |
Aug 13, 2008 |
Engineering Report |
Sep 18, 2008 |
Biologist Report |
Oct 01, 2008 |
Supervisor Biologist SignOff |
Oct 01, 2008 |
Supervisor Engineer SignOff |
Oct 01, 2008 |
Executive Signoff of Staff Reports |
Nov 25, 2008 |
Ready to Schedule Semi-Monthly Meeting |
Dec 11, 2008 |
Mail Agenda Notice |
Jan 13, 2009 |
Council Decision - Denied |
Jan 13, 2009 |
Semi-Monthly Meeting Held |
Jan 13, 2009 |
Semi-Monthly Meeting Date Scheduled |
Jan 23, 2009 |
Petition For Reconsideration Received |
Jan 26, 2009 |
Entry of Appearance Received |
Jan 27, 2009 |
Semi-Monthly Meeting Held |
Jan 27, 2009 |
Continued Application by the Council |
Jan 27, 2009 |
Semi-Monthly Meeting Date Scheduled |
Mar 23, 2009 |
Correspondence Received |
Apr 16, 2009 |
Correspondence Received |
Apr 24, 2009 |
Plans Received |
May 11, 2009 |
Plans Received |
May 19, 2009 |
Ready to Schedule Semi-Monthly Meeting |
May 19, 2009 |
Mail Agenda Notice |
Jun 08, 2009 |
Objections/Comments Received |
Jun 08, 2009 |
Objections/Comments Received |
Jun 08, 2009 |
Objections/Comments Received |
Jun 08, 2009 |
Objections/Comments Received |
Jun 09, 2009 |
Objections/Comments Received |
Jun 09, 2009 |
Objections/Comments Received |
Jun 10, 2009 |
Semi-Monthly Meeting Held |
Jun 10, 2009 |
Council Approval Granted |
Jun 10, 2009 |
Semi-Monthly Meeting Date Scheduled |
Jun 11, 2009 |
Correspondence Received |
Jul 13, 2009 |
Additional Information Received |
Jan 27, 2010 |
Legal Response/Decision |
Feb 02, 2010 |
30 Day Appeal Notification to Owner |
Feb 08, 2010 |
Objections/Comments Received |
Feb 13, 2012 |
Additional Information Received |
May 31, 2012 |
Additional Information Received |
Jun 21, 2013 |
Permit Approved |
Jun 21, 2013 |
Typist for Processing |
Jun 25, 2013 |
Executive Sign Off |
Jun 25, 2013 |
Sent to Photo Copy |
Jul 19, 2013 |
Land Evidence Date |
Feb 16, 2015 |
Modification Request |
Feb 17, 2015 |
Administrative Review for Completeness |
Feb 26, 2015 |
Team Review for Completeness |
Mar 23, 2015 |
Correspondence Received |
Mar 25, 2015 |
30 day Public Notice Issued |
Apr 17, 2015 |
Objections/Comments Received |
Apr 22, 2015 |
Objections/Comments Received |
Apr 24, 2015 |
Objections/Comments Received |
Apr 25, 2015 |
Public Notice End Date |
Apr 27, 2015 |
Application Cancelled |
Apr 27, 2015 |
Biologist Report |
Mar 29, 2016 |
Extension Toll letter mailed |
Apr 08, 2019 |
Extension of Permit Request |
Apr 17, 2019 |
Enforcement Compliance Inspection Required |
Apr 19, 2019 |
Process Extension |
Apr 19, 2019 |
Extension Approved |
May 14, 2020 |
Extension of Permit Request |
Dec 14, 2020 |
Enforcement Compliance Inspection Required |
Dec 22, 2020 |
Process Extension |
Dec 22, 2020 |
Extension Approved |